A Prince Edward County intersection is off-limits to vehicles in a couple separate upcoming blocks of time to finish an infrastructure project.
The intersection of Consecon Street and the Millennium Trail in Wellington will be closed to all traffic during the following times:
- Monday, September 21 at 7 am until Wednesday, September 23 at 7 pm
- Monday, October 5 at 7 am until Tuesday, October 6 at 7 pm.
The municipality will provide additional updates ff there are any changes to the closure schedules.
The closure in September is required so that the County’s contractor can install the watermain (an underground water pipe) and forcemain (a pressurized sewer pipe) across Consecon Street.
During the second closure in October, crews will work to make the final water service connections.
No traffic will be able to pass through the intersection during the closure. The closure will remain in effect continuously, including overnight.
Detour signage will be in place instructing drivers to use Belleville Street/County Road 2, Swamp College Road, Baitleys Road, and Consecon Street. Click here to see the map.
This work is the final connection of the Wellington trunk watermain and sanitary sewer project.
The new trunk watermain will help meet the water distribution and storage needs of the existing residents and future development within the Wellington urban serviced area. The new sewer trunks will accommodate the anticipated increase in wastewater flows from new developments.
For more information, contact the County at 613-476-2148 extension 1023, 613-962-9108 extension 1023, or info@pecounty.on.ca