Today's latest storiesCounty Council set to approve company to provide Marina servicesStreet sweeping and brushing to begin in PEC on TuesdayFraser Park parking lot partially closed for Trenton trunk sewer projectQuinte West seeks community input on the future of Hanna ParkBelleville Theatre Guild: Dave HendersonBeyond the Headlines - what3wordsShelter in Place advisory issued as OPP searched for suspect Sunday night in BathTenders go out for County Road 49 reconstruction in PECDriver escapes vehicle after crash and fire in Quinte WestWinning lottery ticket sold in Lennox and Addington/Frontenac areaQuinte Conservation issues Flood Watch following rainfall on melting snowLost hikers rescued in Quinte West thanks partially to phone appBelleville Council sits for discussion with local MPPs TuesdaySens shut out in crucial road game in UticaSens secure key win in RochesterBelleville Boxer scraps his way to silver at national competitionOntario aiming to help small businesses ease tax impactsStone Mills residents charged in warrant execution by L&A County OPPB&E arrest in Prince Edward CountyRoad reconstruction resuming in Belleville this month

Bridge Street West gas main relocation project in Belleville to last one month

By Hailey MacDonald Sep 9, 2025 | 1:09 PM

The City of Belleville has contracted Enbridge to relocate an existing gas main that currently runs through the middle of the property at 355 Bridge St. West, to the northern and western boundaries of the property (south of Bridge Street West) to allow for the future construction of the new YMCA Centre for Life at the site.

The gas main relocation project is estimated to take a month and is expected to be completed by Oct. 10. The construction of the new YMCA is expected to start following the completion of the gas main relocation.

Future work in this area will be limited to the installation of new twin sanitary forcemains, as part of the ongoing Avonlough Sewage Pumping Station project. At this time, Bridge Street West will not be widened at this location. It will be widened at the Sidney Street intersection as part of the Avonlough Sewage Pumping Station project in the future. Further updates on this project can be on theĀ Avonlough Sewage Pumping Station project page.