Today's latest storiesBelleville Boxer scraps his way to silver at national competitionOntario aiming to help small businesses ease tax impactsStone Mills residents charged in warrant execution by L&A County OPPB&E arrest in Prince Edward CountyRoad reconstruction resuming in Belleville this monthCounty man charged with impairedYMCA Centre for Life continues to build through local philanthropySeveral locals charged in massive drug investigationsInput sought for new multi-use court at Belleville parkLane resigns from head coach/GM of PiratesAthlete of the Week: Tyson CooperCool 100.1 FM Nominated for CMAOntario Radio Station of the Year (Medium Market)Bloomfield woman wins $350,000Spring into Treasure in Downtown BellevilleKingston Police looking for hit and run vehicleCommunity Futures partners launch Transition Program to support business succession planningCZECH POINTS: With baseball comes summer - finallyYouth arrested and charged in Kingston robberyBeyond the Headlines - 2 Air Movements SquadronTyendinaga Police assist Belleville Police in medical distress incident

Mary Street (Picton) closure postponed

By Hailey MacDonald Oct 25, 2025 | 10:35 AM

The full closure of Mary St between Elizabeth St and East Mary St in Picton – originally scheduled for Oct 27-28 – has been postponed.

The contractor, Cobourg Development Services Ltd., is postponing the closure as it waits to receive utility relocate information from Hydro One.

The closure is tentatively scheduled to occur the first week of November. One the date is finalized, the municipality will issue a notice to the public.

The closure is necessary to install new sanitary and storm piping within the Mary St and York St intersection

Project Background:

The municipality is tackling this project on York Street in Picton to ensure nearly 400 residential and commercial properties continue to have reliable sanitary sewer service. This project is a high priority because of the deteriorating condition of a large trunk sanitary sewer that runs underneath York Street.

The project involves replacing the existing sanitary sewer and watermain, installing a new asphalt roadway and sidewalk, and adding a curb and storm sewer to accommodate the curb.

County Council awarded the tender in the amount of $855,941 plus HST for the project on September 23 to Cobourg Development Services Ltd. Council approved the project in the 2024 capital budget.

If you have questions about this project, please contact Jeff Shortt, Project Manager, at 613.476.2148 extension 1007 or email jshortt@pecounty.on.ca.

(HAILEY MACDONALD)