Today's latest storiesPicton Main St reconstruction work concluding for 2025Brighton Fire and Rescue puts smiles on residents facesTwo charged after collision, seizure of drugs and weaponTMHF, youth both benefiting from Holiday Smile Cookie proceedsGet into the spirit of the season with the QW Holiday Home TourThree podium finishes in the Sunshine State for athletes at Picton gymHits 95.5 Interviews: Rachel Murgel, Miss International CanadaAthlete of the Week: Roseanne BlowerMore drivers charged following OPP RIDE checks in Eastern OntarioBeyond the Headlines - policing costs rising everywhereTwo people rescued after falling through ice near KingstonNapanee Budget to Include 3% Tax Increase to Fund Rising OPP CostsDukes steal overtime win ThursdayMotion approved to investigate activity on portion of Picton Terminals propertyHabitat for Humanity recognized by charitable men's groupSeizure of contraband at Collins BayQuinte West Council approves average tax increase of 4.99%Warden, Deputy Warden re-elected in Lennox and Addington CountyCorbyville man charged with impaired driving in single-vehicle collisionCool 100 Interviews: Lee Brice

Picton Main St reconstruction work concluding for 2025

By Hailey MacDonald Dec 12, 2025 | 6:00 PM

RW Tomlinson Limited is concluding work on Phase 3 of the Picton Main St reconstruction project for 2025.

The road returned to two-lane traffic with no signals as of Friday, Dec 12.

This past fall, work crews completed the sanitary and storm sewer work on the west side of the road from #454 County Rd 49 to Fawcett ave. A single layer of temporary asphalt was placed to allow the municipality to reopen the road during the winter months. The surface will be maintained throughout the winter. A new roadway will be installed when the entire project is complete.

RW Tomlinson Limited will resume construction in the spring of 2026 and continue work until Dec 2026. One lane traffic will be maintained at all times and alternate routes will be identified.

Work will include sanitary and storm sewer replacement and extension from Fawcett Ave to Folkard Ln, watermain replacement from #454 County Rd 49 to Folkard Ln, installation of new roadway, curbs, sidewalk, and street lighting from #454 County Rd 49 to Folkard Ln.

The municipality will provide an update prior to construction resuming in the spring. To sign up for notices, click here. Notices will also appear in the local newspapers and on the municipality’s FacebookTwitter, and Instagram accounts.

Visit the project page on the municipal website for more information. If you have an issue during construction, please contact Jeff Shortt, Project Manager, at 613.476.2148 extension 1007 or email jshortt@pecounty.on.ca.